Taking a prioritised opportunity far enough that a capital decision can defensibly be made.
What happens
- Establish the load and demand basis from data
- Compare options genuinely, including doing nothing and doing less
- Produce concept design sufficient to support the estimate and expose integration issues
- Build project economics with sensitivities on the assumptions that actually move the answer
- Decide how performance will be verified, before commitment
What you should have at the end
- A feasibility report with an options comparison and recommendation
- An estimate with its basis and confidence stated
- A risk register
- An M&V strategy agreed before the project is committed
Where this usually goes wrong
The M&V strategy is left until after commissioning. By then the baseline metering that would have made verification possible was never installed, and the saving becomes a matter of assertion. Deciding how you will prove it is part of deciding whether to do it.