Heat — estimating card (Imperial)

Screening-level cost-capacity parameters, PEICI 2026.1. Free to use and cite. No subscription required. Metric edition.

Factor set 2026.1Published 2026-11-01Units ImperialCurrency USDBase region NAStatus seed

Installed cost is estimated from a fitted power law, cost = c_ref × (S / s_ref)ⁿ, using two exponents — one for equipment and one for installed cost. The ratio between them, the installed-cost multiple, therefore falls as capacity rises. It is not a constant, and treating it as one under-prices small plant badly.

Capacities on this card are shown in Imperial units. The reference size and the validity range carry both systems, because those are what you check against the published table. The published JSON is in native units and the exponents are dimensionless — a power law is scale-invariant in S / s_ref, so they are identical in either system. Costs are USD only and never converted.

Published parameters

Equipments_refc_refn_eqpn_instICM at s_refValid range
High-temperature industrial heat pumpMWthNot published — regression pending — DEA Technology Data catalogue treated as licensed on client instruction, 4 September 2026 - the legal block is CLOSEDnot published
Electric boilerMWthNot published — regression pending — DEA Technology Data catalogue treated as licensed on client instruction, 4 September 2026 - the legal block is CLOSEDnot published
Package steam boiler (fossil comparator)lb/hr50,000$236,2760.63180.42482.21310,000–300,000 lb/hr
Electric process heater / furnaceMMBtu/hr70$918,9250.69060.69791.32910–500 MMBtu/hr
Thermal storage tank (partial)gallons500,000$192,0750.73810.62881.50550,000–10,000,000 gallons

Costs are in USD at the source cost year, before any Input Price Relativity. Outside the validity range the calculator refuses rather than extrapolating: a power law fitted over one range does not hold outside it. ICM at s_ref is the multiple at the reference size only — see the worked example for how it moves.

Worked example

Package steam boiler (fossil comparator), at 10,000 lb/hr — the bottom of its validity range.

ratio = 10,000 / 50,000 = 0.2equipment = $236,276 × 0.20.6318 = $85,469ICM = 2.213 × 0.2(0.4248 − 0.6318) = 3.088installed = $85,469 × 3.088 = $263,924

The multiple at this size is 3.088, against 2.213 at the reference size. Applying the reference multiple instead would have returned $189,144 — understating installed cost by 28%. That gap is the reason both exponents are published.

Capacity (lb/hr)EquipmentICMInstalled
10,000$85,4693.088$263,924
50,000$236,2762.213$522,879
300,000$732,9181.527$1,119,334

Accuracy

AACE Class 5 — 0–2% project definition, concept screening.

Expected range: -20% to +30% at best, -50% to +100% at worst. The band is asymmetric and is never averaged into a single ± figure: a screening estimate is far more likely to be exceeded than beaten, and a symmetric band hides that.

Class definition: AACE International Recommended Practice 18R-97.

Input Price Relativity (IPR)

RegionIPRBasket rangeCoverage grade
NA1.000fixed by definitionA
EU0.9570.872–0.975A
APAC0.9310.819–1.014B
SAM0.9310.874–0.938C
MEA0.8870.792–0.964D

Input Price Relativity is an input-price factor. It captures the relative price of equipment, installation labour and bulk materials, plus a productivity allowance. It excludes delivery-environment cost entirely — remoteness, logistics, camp, local-content rules, contractor market conditions, country risk and schedule extension. Those push the other way and none of them is quantified here. Outside a mature industrial region, treat the published factor as a lower bound on the true cost difference.

These values are not validated against any commercial location-factor product. They are derived from published price data and are reproducible from the parameters on the method page.

Delivery Environment Uplift (DEU)

Delivery-environment cost is a separate, project-specific input and is not assessed on a published card. Remote logistics, local-content rules, site access and laydown, contractor-market premium, camp and security, abnormal working, and schedule extension all push cost up, and none of them is in the figures above. Not assessed is not the same as zero.

Sources

  1. Process Equipment Cost Estimation, Final Report, US DOE / NETL, DOE/NETL-2002/1169. Cost year 1998. Licence: US federal — public domain. https://www.osti.gov/servlets/purl/797810/

Using this card

The interactive calculator applies these same parameters, handles unit conversion and Input Price Relativity, and exports a result that records the factor set version. It is at https://pemspring.com/estimating-cards/heat/.

This is the Imperial edition. The Metric edition carries the same data in the other system; the two are the same numbers, because a unit conversion is exact and reversible.

Cite as: Pemspring Energy Solutions, PEICI Heat factor set 2026.1, published 2026-11-01, https://pemspring.com/cost-index/heat/. Historic versions stay addressable so an estimate issued today can be reproduced later.

General material, not engineering advice for a specific site. Order-of-magnitude only. Not a basis for capital approval, for committing to a contractor, or for any decision that a Class 5 estimate cannot carry.