Screening-level cost-capacity parameters, PEICI 2026.1. Free to use and cite. No subscription required. Metric edition.
Installed cost is estimated from a fitted power law, cost = c_ref × (S / s_ref)ⁿ, using two exponents — one for equipment and one for installed cost. The ratio between them, the installed-cost multiple, therefore falls as capacity rises. It is not a constant, and treating it as one under-prices small plant badly.
Capacities on this card are shown in Imperial units. The reference size and the validity range carry both systems, because those are what you check against the published table. The published JSON is in native units and the exponents are dimensionless — a power law is scale-invariant in S / s_ref, so they are identical in either system. Costs are USD only and never converted.
| Equipment | s_ref | c_ref | n_eqp | n_inst | ICM at s_ref | Valid range |
|---|---|---|---|---|---|---|
| Power transformer230/115 kV | 300 | $2,000,000 | 0.75 | — | 1.275 | 75–900 MVA |
| 345/138 kV | 500 | $4,000,000 | 0.75 | — | 1.275 | 75–900 MVA |
| 765/138 kV | 750 | $7,500,000 | 0.75 | — | 1.275 | 75–900 MVA |
Costs are in USD at the source cost year, before any Input Price Relativity. Outside the validity range the calculator refuses rather than extrapolating: a power law fitted over one range does not hold outside it. ICM at s_ref is the multiple at the reference size only — see the worked example for how it moves.
Power transformer, 230/115 kV, at 75 MVA — the bottom of its validity range.
ratio = 75 / 300 = 0.25equipment = $2,000,000 × 0.250.75 = $707,107ICM = 1.275 (held constant)installed = $707,107 × 1.275 = $901,561The multiple here is held constant at 1.275 across the range. That is not a claim that installation scales at the same rate as equipment — it is an admission that no installed-cost regression has been published for this equipment. Where a second exponent exists the card shows the multiple moving; here it cannot, and every result the calculator returns says so.
| Capacity (MVA) | Equipment | ICM | Installed |
|---|---|---|---|
| 75 | $707,107 | 1.275 | $901,561 |
| 300 | $2,000,000 | 1.275 | $2,550,000 |
| 900 | $4,559,014 | 1.275 | $5,812,743 |
Within the 230/115 kV class only. Cost per unit of capacity varies several-fold between classes, so a curve fitted across them describes the sample rather than the equipment.
AACE Class 5 — 0–2% project definition, concept screening.
Expected range: -20% to +30% at best, -50% to +100% at worst. The band is asymmetric and is never averaged into a single ± figure: a screening estimate is far more likely to be exceeded than beaten, and a symmetric band hides that.
Class definition: AACE International Recommended Practice 18R-97.
| Region | IPR | Basket range | Coverage grade |
|---|---|---|---|
| NA | 1.000 | fixed by definition | A |
| EU | 0.957 | 0.872–0.975 | A |
| APAC | 0.931 | 0.819–1.014 | B |
| SAM | 0.931 | 0.874–0.938 | C |
| MEA | 0.887 | 0.792–0.964 | D |
Input Price Relativity is an input-price factor. It captures the relative price of equipment, installation labour and bulk materials, plus a productivity allowance. It excludes delivery-environment cost entirely — remoteness, logistics, camp, local-content rules, contractor market conditions, country risk and schedule extension. Those push the other way and none of them is quantified here. Outside a mature industrial region, treat the published factor as a lower bound on the true cost difference.
These values are not validated against any commercial location-factor product. They are derived from published price data and are reproducible from the parameters on the method page.
Delivery-environment cost is a separate, project-specific input and is not assessed on a published card. Remote logistics, local-content rules, site access and laydown, contractor-market premium, camp and security, abnormal working, and schedule extension all push cost up, and none of them is in the figures above. Not assessed is not the same as zero.
Held in the factor set but not used for any published value on this card: Transmission Cost Estimation Guide for MTEP24 (MISO). Listed so the set's contents can be checked in full — either the reuse licence is unresolved or no fitted parameter draws on it yet.
The interactive calculator applies these same parameters, handles unit conversion and Input Price Relativity, and exports a result that records the factor set version. It is at https://pemspring.com/estimating-cards/grid/.
This is the Imperial edition. The Metric edition carries the same data in the other system; the two are the same numbers, because a unit conversion is exact and reversible.
Cite as: Pemspring Energy Solutions, PEICI Grid & enabling factor set 2026.1, published 2026-11-01, https://pemspring.com/cost-index/grid/. Historic versions stay addressable so an estimate issued today can be reproduced later.
General material, not engineering advice for a specific site. Order-of-magnitude only. Not a basis for capital approval, for committing to a contractor, or for any decision that a Class 5 estimate cannot carry.